| FAQ | Question | Slide |
|---|---|---|
| FAQ 1 | Latest finding: where has the building settled, and where is it heading? (MN55 contour and graphs) | 2-5 |
| FAQ 2 | Settlement is still increasing: steeper or leaner? And the lean of the building | 6-7 |
| FAQ 3 | After completion, will settlement keep increasing? Do we keep monitoring? | 8-9 |
| FAQ 4 | Should construction continue? On record: requests to the Substructure Engineer | 10-11 |
| FAQ 5 | What has happened, and when? (chronology) | 12 |
| FAQ 6 | Who must give the allowable settlement values? | 13 |
| FAQ 7 | Is the building safe? (rev 1, MN55) | 14-16 |
| mm per floor cast | Level 31 to 33.6 | Level 33.6 to 37.6 |
|---|---|---|
| BSM10 | 4.4 | 4.6 |
| BSM1 | 4.6 | 4.3 |
| BSM9 | 4.2 | 4.2 |
| Stage | What we watch |
|---|---|
| Now to roof | Every cycle: settlement, the three pairs and the tilt per floor cast (as in WKE/18), Syarikat Ayob as the independent check |
| Roof to completion | Settlement per month as floors stop; finishes and services still add load |
| After completion | Settlement per month falling over several readings; estimate of the final settlement by standard methods once the load is steady (Asaoka 1978; hyperbolic method, Tan 1971) |
| Any time, including after completion | If the tilt or any pair 30 m or more apart (BSM1 and BSM4, BSM6 and BSM9, BSM2 and BSM10) reaches 1/1000, or distress or structural cracking is seen: a formal review is called for, and the Substructure Engineer reviews the foundation |
| Stop monitoring | When the rate stays below a value the Substructure Engineer gives (not yet part of the request in WKE/18 para 7) |
| Date | Letter or report | What HIZ asked |
|---|---|---|
| 17 Oct 2025 (e-mailed 18 Oct) | HIZC/24.05/WKE/7 + SM/03 | After a rise of about 9 mm at BSM10 (MN11 to MN12): readings to be reviewed by the substructure package engineer; WKE to notify UDA Land (North) for the Package 1 foundation review (para 2(d), 2(e)) |
| Oct 2025 to May 2026 | Reports SM/03 to SM/06 | Review of the settlement requested again |
| 12 May 2026 | HIZC/24.05/WKE/9 | Precautionary notice; asks WKE to consult the Substructure Engineer |
| 18 May 2026 | HIZC/24.05/WKE/10 | Asks again for the Substructure Engineer's values |
| 3 Jul 2026 | HIZC/24.05/WKE/14 | Interim levels set; Substructure Engineer's values and comments asked |
| 12 Oct 2026 | HIZC/24.05/WKE/16 + SM/10 | Asks again for the Substructure Engineer's values |
| 30 Oct 2026 | HIZC/24.05/WKE/17 + SM/11 | Formal review called for; formal written reply asked on items a to f |
| 9 Nov 2026 | HIZC/24.05/WKE/18 | Latest findings; request restated in full, copied to the Substructure Engineer |
| To date | Substructure Engineer | No written reply with the allowable values received (10 Nov 2026) |
| Date | Event | Reference |
|---|---|---|
| A. Monitoring and requests to the Substructure Engineer | ||
| 16 Oct 2024 | Settlement monitoring starts (MN0) | Nattest Lab |
| 17 Oct 2025 | After a rise of about 9 mm (MN11 to MN12), HIZ asks, through WKE, for the readings to be reviewed by the substructure package engineer (e-mailed 18 Oct) | WKE/7, SM/03 |
| 12 May 2026 | HIZ precautionary notice; independent Licensed Land Surveyor asked to counter-check | WKE/9 |
| 13 May 2026 | UDA Land (North): angular distortion, not total settlement alone, governs assessment | UDA (81) |
| 18 May 2026 | HIZ asks again for the Substructure Engineer's values | WKE/10 |
| 9 Jun 2026 | MN27: Nattest Lab and Syarikat Ayob records consistent | SM/07 |
| B. Resumption under monitoring | ||
| 23 Jun 2026 | Works may proceed under continued monitoring, pre-set levels for formal review | WKE/13, SM/07 |
| 25 Jun 2026 | Meeting at UDA HQ: HIZ and NMI & Associates (Independent Checker) present findings | UDA (90) |
| 30 Jun 2026 | UDA Land (North) instructs resumption of works | UDA (90) |
| 3 Jul 2026 | HIZ interim levels for formal review; Substructure Engineer's values asked | WKE/14 |
| 22-23 Sep 2026 | Independent Checker report received | UDA (108) |
| 12 Oct 2026 | Report SM/10 submitted; values asked again | WKE/16 |
| 16 Oct 2026 | Ir. Nazri (NMI): allowable values to be set by the foundation engineer | Discussion |
| C. Latest | ||
| 30 Oct 2026 | Report SM/11 (to MN54): formal review called for; 1/1000 applied to pairs 30 m or more and to tilt | WKE/17 |
| 3 Nov 2026 | MN55: BSM10 84.23 mm; Syarikat Ayob surveys the same day | NTP26/0374, NO-SM-39 |
| 9 Nov 2026 | Latest findings (MN55); request to the Substructure Engineer restated in full | WKE/18 |
| Quantity | MN55 | Value HIZ applies, or reference | Roof (slab 41), trend |
|---|---|---|---|
| Tilt of the building | 1/1409 | 1/1000 (BS EN 1990:2023 Tables A.1.15, A.1.16, buildings 100 m or taller) | about 1/1210 (range to 1/1140) |
| Angular distortion, worst pair 30 m or more (BSM1 and BSM4) | 1/1204 | 1/1000 (WKE/17); for reference 1/667 framed buildings (Table A.1.14), 1/500 (BS EN 1997-1 Annex H) | about 1/1060 (upper edge 1/990) |
| Largest settlement difference (BSM4 to BSM10, about 72 m apart) | 52.45 mm | No value given. Reference: 100 mm for utility connections only (BS EN 1990:2023 Table A.1.13); not monitored | |
| Total settlement, highest (BSM10) | 84.23 mm | No allowable value given by the Substructure Engineer. Reference: up to 50 mm often acceptable for normal structures on isolated foundations (Annex H(4)) | still increasing |